East Anglia ONE Document Library

Breadcrumb

East Anglia ONE North Document Library

East Anglia ONE North Document Library

Below you will find the historic documents relating to the development and consultation activities for East Anglia ONE North.

East Anglia ONE North Document Library faq

East Anglia ONE North Planning Application and Examination Documents

The East Anglia ONE North project submitted an application for development consent in October 2019. The Planning inspectorate held an examination for the project from October 2020 to July 2021. 

The documents associated with the planning application and examination for East Anglia ONE North are available for download on the Planning Inspectorate website (opens in a new window).

Preliminary Environmental Information

East Anglia ONE North Limited published the Preliminary Environmental Information Report (PEIR) for the proposed East Anglia ONE North project in accordance with Section 42 of the Planning Act 2008 and presented at Phase 4 Consultation. The documents that comprise this report are available below.

We have supplied guidance documents to support with reviewing the documentation as follows:

(It should be noted that these documents are intended to serve only as supplementary information to the PEIR and do not form part of the formal package of documentation issued for the Section 42 consultation process.)

 

Non-Technical Summary and Guidance Document

 

Volume 1: Chapters

 

Volume 2: Figures

 

Volume 3: Appendices

Phase 4 Consultation - 2019

Phase 4 of our community consultation ran from 11 February 2019 and closed on 26 March 2019. We held a series of Public Information Days to provide members of the public with an update on the progress of the East Anglia TWO and ONE North Projects and an opportunity to give feedback to the development team.

Two Public Information Days were held in each of the following locations:

  • Friston
  • Aldeburgh
  • Leiston
  • Orford
  • Knodishall
  • Thorpeness
  • Southwold

All Phase 4 Consultation Material can be found below:

3D Flythrough Video Notes

- View the notes for this video

We also published the Preliminary Environmental Information Report (PEIR) for the proposed East Anglia TWO project in accordance with Section 42 of the Planning Act 2008. This can be viewed in the section above.

View our Phase 4 Community Consultation Summary Report here (opens in a new window)

Phase 3.5 Consultation - 2018

Phase 3.5 Consultation began on 29 September and closed on 12 November 2018 (extended by two weeks from the original end date of 29 October).

Phase 3.5 Consultation was an additional stage of consultation to consult primarily on a new potential substation location between Sizewell and Leiston, as a possible alternative to the currently proposed substation site near Friston. 

Public meetings were held in the following locations:

  • Leiston
  • Friston
  • Knodishall
  • Thorpeness

All Phase 3.5 Consultation information can be found below:

You can view the Phase 3.5 Decision Summary document here.

Phase 3 Consultation - 2018

Phase 3 of our community consultation took place from 16 May until 28 August 2018. The key focus of Phase 3 was to consult on our Indicative Onshore Development Area, which can be found here (opens in a new window). In particular we welcomed your views on any mitigation that may be required.

Two Public Information Days were held in each of the following locations:

  • Orford
  • Friston
  • Leiston
  • Southwold
  • Lowestoft
  • Aldeburgh
  • Thorpeness

The materials shown at the Phase 3 Public Information Days can be viewed using the links below:

Our Phase 3 PIDs Summary Report can be viewed here. (opens in a new window)

Phase 2 Consultation - 2018

Phase 2 of our community consultation concluded on 17 April 2018. Throughout the consultation period Public Information Days were held in the following locations:

  • Lowestoft
  • Southwold
  • Leiston
  • Thorpeness
  • Aldeburgh
  • Orford

Supporting material presented at the Public Information Days can be viewed using the links below:

A summary report of the Phase 2 Consultation information days has been prepared to present the feedback received and can be viewed here:

Following the conclusion of the Phase 2 community consultation process, ScottishPower Renewables prepared a report outlining our approach to site selection. The work our expert advisors have undertaken to inform the site selection, how we make our decisions and ultimately, the preferred zone selected for the location of the two substations (one each for East Anglia TWO and ONE North) and one National Grid Energy Transmission Substation.

This report includes links to supporting materials and can be viewed here:

Phase 1 Consultation - 2017

Phase 1 of community consultation (non-statutory) concluded in late 2017. A series of Public Information Days ran throughout October and November to introduce the project to the community at the following locations:

  • Southwold
  • Leiston
  • Lowestoft
  • Orford

Supporting materials presented at Phase 1 Consultation consisted of:

You can also view the East Anglia ONE North Summary of Environmental Considerations document here (opens in a new window).

Scoping Report

As part of the consenting process we submitted Scoping Reports for East Anglia TWO and East Anglia ONE North to the Planning Inspectorate (PINS) for their consideration in November 2017. These Scoping Reports requested a scoping opinion to agree the methodology for undertaking the full Environmental Impact Assessment (EIA). These assessments form part of the Environmental Statement which will be submitted as part of the full Development Consent application.

The Scoping Reports provided a clear description of our proposed infrastructure, and connection route to the electricity transmission network. The scoping process also sought stakeholder opinions on the areas to be investigated in detail when undertaking our Environmental Impact Assessments.

Statement of Community Consultation

In accordance with Section 47 of the Planning Act 2008, East Anglia ONE North Limited published a Statement of Community Consultation in March 2018 outlining our approach to consulting with local communities on the East Anglia ONE North offshore windfarm.

In September 2018 ScottishPower Renewables published an Updated Statement of Community Consultation to include an additional phase of consultation (Phase 3.5) that took place from 29 September to 12 November 2018.

East Anglia ONE North Limited (EAONL) have received a Section 105 Notice from Secretary of State requiring the production of a high-level Decommissioning Programme in line with relevant international obligations and compliant with UK legislations and associated consultation process.

The East Anglia ONE North Offshore Wind Farm Order 2022 (2022 Order) granted consent on 31 March 2022 for the development of an offshore windfarm. The consent for East Anglia ONE North has since been amended in December 2022.

The purpose of the Decommissioning Programme is to provide preliminary information on the methods and approaches to how the offshore components will be decommissioned at the end of the operational lifetime of the Project.

The Section 105 Notice requires EAONL to carry out consultation before submitting the Decommissioning Programme to the Secretary of State. This includes carrying out consultation with prescribed bodies and making the proposals publicly available for at least 28 days in order to obtain feedback on the draft Decommissioning Programme.

Therefore, in accordance with the Section 105 Notice, the draft Decommissioning Programme will be made publicly available for 28 days from 19 December 2025 here.

Any enquiries on the documents can be sent to EAONL by email on eastangliaonenorth@scottishpower.com or by post to East Anglia ONE North Decommissioning, 320 St Vincent Street, Glasgow, G2 5AD

The Decommissioning Programme will provide a summary table of the comments and actions taken following receipt and consideration of the consultation responses. Please note that any responses received by EAONL will be handled in compliance with the European Union’s General Data Protection Regulation and published with all personal information removed.

The deadline for the receipt of representations is 11.59pm, 15 January 2026.