MachairWind, located Northwest of Islay and West of Colonsay, will be SPR’s first offshore windfarm of its kind in Scottish waters. MachairWind’s offshore turbines will export their green electricity to the grid by a subsea cable that will connect to a substation in the vicinity of Girvan, South Ayrshire.
MachairWind submits its consent applications for the Windfarm Development Area (WDA) in 2026; it is anticipated a decision will be made by Scottish Government in 2027. MachairWind will continue to engage with stakeholders, communities, and potential supply chain partners over the coming months and years.
- MachairWind
- Iona
- Ross of
Mull - Colonsay
- Jura
- Islay
- Oban
- Greenock
- Glasgow
- Campbeltown
- Ayr
Project Characteristics
- Around 2 gigawatts
- 91 to 144 turbines (Capacity 15MW to 24MW)
- 53 Water depth
- Fixed bottom foundations
- 280m to 335m max blade tip height*
- Site area 448km
*Maximum blade tip height above Lowest Astronomical Tide (LAT)
Viewpoints - Photomontages
Project timeline
Completed Upcoming
-
2021 to 2023, completed
Progressed with technical and environmental surveys, feasibility studies and community stakeholder engagement.
-
2022, completed
MachairWind entered into its Option to Lease Agreement with Crown Estate Scotland.
-
2023 to 2024, completed
First Site investigation campaign and one year metocean campaign completed.
-
Jan 2025, completed
Windfarm Development Area (WDA) Scoping Opinion received from Marine Directorate.
-
July 2025, completed
Second Site Investigation Survey of WDA completed.
-
May to July, completed
First round of pre-application consultation for WDA completed.
-
Oct to Nov 2025, completed
Second round of pre-application consultation for WDA completed.
-
2026, completed
Consent applications submitted for the WDA.
-
2027, upcoming
Consent decision for the WDA, whether accepted or rejected.
-
Early to 2030s, upcoming
Construction to start.
-
Early to mid 2030s, upcoming
First export of power from the windfarm anticipated. Community Benefit Fund will be live.