Kilgallioch

Project Details
Location located in and around Kilgallioch and Purgatory Forests, 5 kilometres south of Barrhill, South Ayrshire and 5 kilometres north east of New Luce, Dumfries and Galloway
Stage

Construction underway

No. Turbines 96 Gamesa turbines
Operating Capacity up to 239 megawatts
Latest News

Initial works have concentrated on establishing the site construction compound to effectively support and manage the execution of the project. Work on the onsite substation platform is also underway.

Turbine access roads and turbine foundation works will begin in early August 2015. With timber felling works within the south of the site due to commence in late August 2015.

The civil built programme is anticipated to run for 12 months with wind turbine deliveries, erection and commissioning works combining to provide for an overall build programme of 26 months.

Project History Consent granted by the Scottish Government in February 2013
Contact The project team can be contacted by calling 0845 030 3002 or alternatively by email.

Interactive Map

Anticipated views of the windfarm available here